AIP SUP
20/23
|
Effective from 05 DEC 2023
Published on 05 DEC 2023
|
| |
|
CONSTRUCTION WORK AT KAOHSIUNG INTL AIRPORT
|
Estimated construction period is through DEC 2025. Individual construction phase will be activated by NOTAM and may not follow a numeric sequence.
|
|
|
-
RWY 09/27 closed.
-
All Taxiways closed.
-
The airport is only available for emergency medical service helicopter under conditions.
-
The airport is not to be used for technical landing or not to be requested as an alternate for flight planning.
|
|
|
-
TWY A closed between RWY 09/27 and TWY S (excluded).
-
New TWY J is available for entry/exit RWY. Please refer Phase 7.
-
ACFT using RWY 27 to land or abort take-off, if exceeding TWY J, shall not make a 180-degree turn on runway, inform TWR for towing service from runway to the apron instead.
-
Reference map of closed area
|
|
|
|
|
-
TWY F closed.
-
ACFT using RWY 09 to land or abort take-off, if exceeding TWY E, shall not make a 180-degree turn on runway, inform TWR for towing service from runway to the apron instead.
-
Reference map of closed area
|
|
|
|
|
TWY S closed between TWY J (excluded) and TWY B (excluded).
|
|
|
|
|
The intersection of TWY A and TXL A2 closed.
|
|
|
|
|
|
|
|
|
|
|
|
|
滑道名稱
Taxiway Designator
|
寬度
Width
|
鋪面
Surface
|
強度
Strength
|
|
J
|
30 M |
CONC |
Issued by NOTAM |
|
|
|
|
交叉口起飛 / INTERSECTION TAKE-OFF
|
跑道名稱
Designations RWY
|
TWY |
TORA
(M)
|
TODA
(M)
|
ASDA
(M)
|
|
09
|
J |
3056 |
3116 |
3116 |
|